23:00: Arrival in Bergen.
Friday, August 22", 2014
Disassembly of the oceanographic equipment related to the SF measurements and
dismounting of the SF, all parts are flushed with fresh water, dried, and finally mounted
together again. Chemical analyses and reprocessing of the last water samples for RA and
metals.
Saturday, August 23'°, 2014
Continuations of the works from the previous day.
16:00: Exchange of the transport containers between forecastle and main deck by a land-
based mobile crane.
Sunday, August 24", 2014
16:00: Arrival of a new science crew for the second leg. Handover of the chemistry labs and
logistic arrangements for the second leg. Preparation of next days the crew change.
Monday, August 25", 2014
Crew change and return flight to Hamburg via Copenhagen.