Part B - Verifications and approval requirements
[Doc. No. 342]
[Doc. No. 343]
Supplementary reports to the geotechnical design report and other verified
reports in compliance with BHS stipulations
Verification report(s) pertaining to Docs. No. 340, 341 and 342.
3.5 Operating phase
3.5.1 Preliminary remarks
Foundation elements are not subject to any specific operating requirements during the opera
tion of the installation once they have been appropriately and professionally installed.
In order to monitor the overall behaviour of the foundation elements during the operating
phase, parameters, such as shifting, deformation, component stress and frequencies, shall be
measured and recorded (monitoring) in the area of the foundation elements at representative
offshore wind turbine sites. These sites shall be selected in coordination with the geotechnics
expert. Based on these results, the compliance of the interaction between the subsoil and the
structure with the design and planning results shall be regularly examined and assessed by an
expert within the scope of the periodic inspections.
For all types of offshore structures, special requirements resulting from specific installation
results or special demands as a result of innovative new foundation principles may arise dur
ing the normal operations.
For measures introduced during normal operations, the level of stability of the foundation ele
ments against collapse is generally verified using the observation method.
3.5.2 Technical codes of practice
The geotechnical codes of practice to be applied during the operating phase are derived from
DIN EN 1997 (EC 7) and the references contained therein and comply with the features of the
foundation elements contained in the specific design documentation.
3.5.3 Requirements and required verifications
The requirements and required verifications shall comply with the respective project-specific
stipulations resulting from the approvals, permits, authorisations and orders issued by the
BSH.
3.5.4 Documents to be submitted for maintaining the operating permit
The documents to be submitted with respect to maintaining the operating permit, shall com
ply with the respective project-specific stipulations resulting from the approvals, permits, au
thorisations and orders issued by the approval authority responsible for granting the operating
permit.