8
Part A - Introduction
Further work processes are documented in the following reports and supporting documents:
Construction of foundation work -> Protocols and assessments
Monitoring of foundation work -> Report of findings and assessments
Report of findings and assessments -> Report of findings and assessments
The integration of appropriate work steps in ground investigations and assessments within
the phases corresponding to the chronology of events in accordance with the Standard De
sign are illustrated in Table 2.
Table 2: Objective and type of geotechnical survey and investigation. The chronology corre
sponds to the project phases for implementing an offshore wind farm project in accordance
with the Standard Design.
Phase
Measure
Purpose and objec
tive of exploration
Type of exploration
Work steps/support
ing documents
Develop
ment
Detailed
clarification
for the site;
Planning
including
preliminary
design of the
structure of
the plant
- Preliminary investi
gation of the area;
- Site selection and
preliminary planning
of structures;
- The preliminary in
vestigation aids de
cision-making as to
whether the planned
offshore structures
can be built with re
gard to the ground
conditions, and if
necessary also
which general re
quirements are es
sential for the foun
dation concepts, the
foundation structure
and the construction
process and which
measures are impor
tant for site investi
gations.
- Fundamentals for
invitations to tender
on foundation plan
ning and construc
tion
- Review, assess
ments and evalua
tions of available
supporting docu
ments;
- Geological survey in
the entire area of the
construction site;
- Preliminary geo
technical investiga
tions, i.e. represent
ative exploration by
means of direct and
indirect exposures
(a coarse grid over
the construction
site) and representa
tive determination of
the essential param
eters and character
istics of the ground
conditions.
- Evaluation of availa
ble supporting doc
uments;
- Geological survey;
- Preliminary geo
technical investiga
tions (drilling and/or
probing, laboratory
and/or field tests);
Supporting docu
ments to be submit
ted with the design
basis and the prelim
inary design:
- Geological report,
- Preliminary geo
technical site survey
report,
- Soil and foundation
expertise (Develop
ment phase).
All documents audited
by an inspector